Construction team started working on the 13th floor of Section 3

07-11-2018

Obolon Residences construction team is already working on monolithic structures of the 13th floor from the ground level (the 11th residential floor) and on a water isolation of the lobby and the 2nd entrance ramp to the stylobate of Section 3. We have finished the brickwork on the 1st, 2nd and most of the 4th floor. In October we used about 680 sqm of concrete and 135 tons of reinforcement steel. 

On the Obolon Residences construction site for the first time in Kiev there is a lift with 2 hoisting boxes. Its capacity is 2 tons and speed is 0.5 m/s. Such a lift can be installed on objects up to 200 m high, so it will reach the last 27th floor of Section 3. It helps to reduce time for lifting both workers and construction cranes, as well as parts of structures.